Sunnaas Rehabilitation Hospital is in need of renovation of their buildings, including a new wing. SINTEF has been involved in establishing the master plan for the hospital which is followed when a new wing will be built according to the available investment funds.

Sunnaas Rehabilitation Hospital
Sunnaas Rehabilitation Hospital. Photo: Tore Schrøder

SINTEF's task is to ensure that the functional requirements addressed in the master plan are fulfilled, and help the project to meet the requirements set by the South-Eastern Regional Health Authority.

The new wing is phase two in the building process. SINTEF is also involved in preparing for phase three.

Published 11 September 2013
Senior Adviser

Project duration

01/01/2012 - 31/12/2015