Optimal Solutions for Protection, Control and Automation in the Power System

The purpose of the project was to contribute to finding optimal investments in protection, control and automation (PCA) in the power system, reduce costs related to operation and maintenance, and control interruption costs.

Contact person

The project covered all grid levels, 1 – 420 kV.

The project had two subprojects:

  • Opportunities and potentials of new technology (PCA and ICT) and functionality
  • Methods, models and decision support for finding optimal PCA solutions 

Brochure about the project

Results:

Technical reports:    

  • Gjerde, O.; Kjølle, G.H.; Samdal, K.; Heggset, J.:
    Methodology for calculating the reliability of protection and control equipment
    SINTEF Energy Research 2007 (TR A6467, EBL-K 233-2007)
  • Gjerde, O.; Langdal, B.I.; Kjølle, G.H.; Aabø, Y.:
    Utilisation of numerical technology for protection, control and automation - A conceptual description
    SINTEF Energy Research 2005 (TR A6172, EBL-K 191-2005)
  • Kjølle, Gerd; Heggset, Jørn; Gjerde, Oddbjørn; Hjartsjø, Bjørn Tore: Fault statistics for protection, control and automation equipment 1-420 kV
    SINTEF Energy Research 2003 (TR A5739, EBL-K 98-2002)

Articles:

Other publications:    

  • Haugen, Arild:
    Reliability analysis of protection in the power grid
    Master's thesis, NTNU, spring 2005
     

The project was one of the subprojects under the area "Quality-appropriate and cost-effective energy systems" at EnergiNorge.

Participants:   

  • EnergiNorge
  • The Research Council of Norway
  • Statnett SF
  • Grid companies

Performed by:

  • SINTEF Energy AS 
  • NTNU

Key facts

Project duration

2002 - 2006

Explore research areas